- Home
- Government
- Departments
- Public Works
- Engineering and Capital Projects Division
- Capital Improvement Projects
- IDOT Wolf Road Reconstruction Project
IDOT Wolf Road Reconstruction Project
General Information
IDOT Letting | March 6, 2020 |
Contractor | Acura, Inc. |
Project Manager: | Glen Pennington, PE Illinois Department of Transportation 630-816-5940 |
Estimated Project Cost: | $13,000,000.00 |
Work resumes | March of 2022 |
Project Information
This Project Includes:
- Total roadway and right of way reconstruction, including the replacement of the 2-lane asphalt road with a concrete 3-lane roadway. Existing drainage ditches will be replaced with underground storm water pipe.
- Modernization of 2 signals on Dundee Road and 1 signal on Wolf Road will be accomplished assisting emergency responses. These improvements include emergency vehicle preemption (EVP) devices on all signals, and permanent signal structures installed at Strong Street.
- Repair of existing 5’ wide sidewalk and installation of additional sidewalk.
- The project will entail substantial construction activity including regrading within most of the existing right of way area, removal of all existing asphalt and roadway base material. Improvement of the roadway in an expedited way will require detouring southbound Wolf Road traffic, and incorporating a one-way traffic route northbound for approximately six (6) months due to the complicated nature of the project construction. After that 6 month period, a 2-way traffic pattern would resume for the balance of the project. Limited 2-way traffic would be allowed near major intersections during the 6 months. Southbound Wolf Road traffic during this period would be diverted with detour signage.
Project Limits: Milwaukee Ave South to just North of Hintz Road
Project Schedule: 2020-2022
Project Updates:
2-10-2022: Acura is going to start construction operations on Monday February 28th weather permitting. Manchester Drive at Wolf Road will be closed first to complete storm sewer and earthwork operations. Once this work is complete Acura will open Manchester Drive at Wolf Road and then Crescent Drive will be closed at Wolf Rd. This is expected to be completed by the end of March. At that time similar work will be completed on Highland Avenue at Wolf Road. As the construction work gets closer, additional updates will be provided.
12-9-2021: As of Friday December 3rd, Strong Ave has been opened back up again and all water and sewer work in this area is complete. Temporary asphalt pavement has been placed in this area for the winter. Construction activities are wrapping up for the year and will commence again in the spring.
10-28-2021 - Update
Click Here to download the Phase 2 latest notice and map (PDF)
Acura has started removing the temporary northbound asphalt lane on the east side of Wolf Road north of Dundee Road. Temporary driveways will be installed by the contractor for residents to retain access to their home or business. Strong Avenue access to Wolf Road is closed on the east side of Wolf Road while water main and storm sewer work is completed. This is expected to last 6 weeks. Strong Avenue access to Wolf Road will be opened back up before winter. Please see diagram for most details on the location of this work.

10-8-2021: Phase 2 Traffic Switch on Wolf Road will take place in the afternoon on Friday, October 8, 2021.
-Phase 2 of IDOT's Wolf Road Reconstruction Project is expected to begin October 8th, weather depending. If rain continues to delay, it will be pushed off a day at a time until clear weather allows the switch to take place. Phase 2 will allow traffic to flow freely one line in each direction (north and south) on Wolf Road. All residential and commercial driveways will either have permanent or temporary access to Wolf Road. Towards the end of October additional underground utility work is expected to start at Strong Avenue and East Manchester Drive. Additional notices will be provided once that schedule is known.
-All side streets will be opened during the beginnning of Phase 2. This includes Picardy Land and Mayer Ave.
-Strong Avenue will remain completely open. Towards the end of October expect closures on the east side of Strong Avenue at Wolf Road for water main and storm sewer work. Additional notice will be provided when this schedule is better known.
Click here to download the IDOT Wolf Road Phase 2 Traffic Configuration (PDF)


9-22-21: Phase 1 of the Wolf Rd. project will be complete within the next 2-3 weeks. Below is a tentative schedule for roadway openings and closures along the Wolf Rd. corridor north of Dundee Rd.
-Meyerson Way is expected to reopen on September 23rd.
-Picardy Lane is now required to remain closed until Phase 1 of this project is complete which is expected the second week of October.
-Strong Avenue is expected to reopen on September 27th.
-Mayer Avenue will be closed when Strong Avenue is opened in order to maintain sufficent access to the adjacent neighborhood.
Below is an exhibit outlining these scheduling changes.
Wolf Road Road Closure Exhibit
5-28-21: Delays in construction have pushed the water main work on Strong and Wolf Rd. until June 7th. This work is expected to last 2-3 weeks. Updates will be provided as the project moves forward.
4-23-21: As of Friday, May 14th access to westbound Strong Ave. from Wolf Rd. will be closed due to water main installation and construction. Access to Wolf Rd northbound from Strong Ave. on the west side of Wolf Rd. will also be closed. You can still access Wolf Rd. northbound from Strong Ave. on the east side of Wolf Rd. This closure is expected to last for 3 weeks. Mayer Ave. to the north will still remain open to provide access to the subdivision to the west.
IDOT Wolf Road Reconstruction Notice
PACE ROUTE 234 Wolf Road Detour Notice - Effective March 22, 2021
Project Updates:
2-10-2022: Acura is going to start construction operations on Monday February 28th weather permitting. Manchester Drive at Wolf Road will be closed first to complete storm sewer and earthwork operations. Once this work is complete Acura will open Manchester Drive at Wolf Road and then Crescent Drive will be closed at Wolf Rd. This is expected to be completed by the end of March. At that time similar work will be completed on Highland Avenue at Wolf Road. As the construction work gets closer, additional updates will be provided.
12-9-2021: As of Friday December 3rd, Strong Ave has been opened back up again and all water and sewer work in this area is complete. Temporary asphalt pavement has been placed in this area for the winter. Construction activities are wrapping up for the year and will commence again in the spring.
10-28-2021 - Update
Click Here to download the Phase 2 latest notice and map (PDF)
Acura has started removing the temporary northbound asphalt lane on the east side of Wolf Road north of Dundee Road. Temporary driveways will be installed by the contractor for residents to retain access to their home or business. Strong Avenue access to Wolf Road is closed on the east side of Wolf Road while water main and storm sewer work is completed. This is expected to last 6 weeks. Strong Avenue access to Wolf Road will be opened back up before winter. Please see diagram for most details on the location of this work.
10-8-2021: Phase 2 Traffic Switch on Wolf Road will take place in the afternoon on Friday, October 8, 2021.
-Phase 2 of IDOT's Wolf Road Reconstruction Project is expected to begin October 8th, weather depending. If rain continues to delay, it will be pushed off a day at a time until clear weather allows the switch to take place. Phase 2 will allow traffic to flow freely one line in each direction (north and south) on Wolf Road. All residential and commercial driveways will either have permanent or temporary access to Wolf Road. Towards the end of October additional underground utility work is expected to start at Strong Avenue and East Manchester Drive. Additional notices will be provided once that schedule is known.
-All side streets will be opened during the beginnning of Phase 2. This includes Picardy Land and Mayer Ave.
-Strong Avenue will remain completely open. Towards the end of October expect closures on the east side of Strong Avenue at Wolf Road for water main and storm sewer work. Additional notice will be provided when this schedule is better known.
Click here to download the IDOT Wolf Road Phase 2 Traffic Configuration (PDF)
9-22-21: Phase 1 of the Wolf Rd. project will be complete within the next 2-3 weeks. Below is a tentative schedule for roadway openings and closures along the Wolf Rd. corridor north of Dundee Rd.
-Meyerson Way is expected to reopen on September 23rd.
-Picardy Lane is now required to remain closed until Phase 1 of this project is complete which is expected the second week of October.
-Strong Avenue is expected to reopen on September 27th.
-Mayer Avenue will be closed when Strong Avenue is opened in order to maintain sufficent access to the adjacent neighborhood.
Below is an exhibit outlining these scheduling changes.
Wolf Road Road Closure Exhibit
5-28-21: Delays in construction have pushed the water main work on Strong and Wolf Rd. until June 7th. This work is expected to last 2-3 weeks. Updates will be provided as the project moves forward.
4-23-21: As of Friday, May 14th access to westbound Strong Ave. from Wolf Rd. will be closed due to water main installation and construction. Access to Wolf Rd northbound from Strong Ave. on the west side of Wolf Rd. will also be closed. You can still access Wolf Rd. northbound from Strong Ave. on the east side of Wolf Rd. This closure is expected to last for 3 weeks. Mayer Ave. to the north will still remain open to provide access to the subdivision to the west.
IDOT Wolf Road Reconstruction Notice
PACE ROUTE 234 Wolf Road Detour Notice - Effective March 22, 2021
Communications
Notify Me: Residents within the construction areas are encouraged to sign up for Notify Me to receive periodic updates regarding construction in their area. Click here to sign up.
Newsletters & Notices: Periodically newsletters and notices are distributed to residents to keep them apprised of current and upcoming construction related events.