Chaddick Drive Resurfacing

General Information

Tentative Start Date: May 3, 2023
Tentative Completion Date:June 14, 2023
Bid Opening:March 17,2023 
Project Manager:Kevin Pelli
Contractor:Builders Paving, LLC
Awarded Contract Amount:$392,000.00
Funding Sources:Rebuild Illinois Funds


Project Information

 

 

This Project Includes: Removal and replacement of concrete curbs and sidewalks, milling of the existing asphalt and resurfacing with new Hot-Mix Asphalt.

Project Limits: Marquardt Dr to Hintz Road

Chaddick
Updates
5-3-23: Concrete contractor began removal of the curbs and sidewalks to be replaced.

5-5-23: Concrete contractor poured 72 CY of concrete curb on the east and west sides.

5--15-23: Concrete contractor poured  the other halves of driveway curbs that were not done last week.