2023 MFT Program

General Information

Tentative Start Date May 17, 2023
Tentative Completion Date August, 25, 2023
Bid Opening March 23,2023
Project Manager Kevin Pelli
Contractor Builders Paving, LLC
Awarded Contract Amount 1,678,000.00
Funding Sources MFT, TIF and Storm Sewer Funds

Project Information

Roads to be resurfaced: 3rd Street, 2nd Street, 1st Street, Mayer Ave, E.Norman Ln, Fletcher Dr, Sarah Ct, Anthony Rd, Robert Ave, Thelma Ct, Albert Ter, Blaze Tr, Peace Dr (Blaze to Rose), Crimson Dr (S. of Twilight to Blaze) and Weeping Willow Dr (Honeysuckle to Willowbrook).

* Twilight Lane and Maureen Drive are not being resurfaced this year. 

This Project Includes: The work consists of HMA surface removal, Class D patching, utility structure adjustment, drainage structure removal and replacement, combination concrete curb and gutter removal and replacement, sidewalk removal and replacement, ADA ramp replacement, HMA surface course placement, landscape restoration, and all incidental and collateral work work necessary to complete the project. 

Project Location:

MFT

Updates:

5-16-23: Saw cutting on this year's 2023 MFT project did commence today as expected.

5-17-23: All curb marked for removal and replacement on the NPTSOS on Weeping Willow, Peace, Blaze and Crimson was removed.

5-18-23: All of the removed curb on Weeping Willow, Peace, Blaze and Crimson was framed for concrete pouring