2017 Watermain Replacement &  Roadway Improvement Program

General Information

Tentative Start Date: 05/15/2017
Tentative Completion Date: TBD
Bid Opening: 04/05/2017
Project Manager: Lana Rudnik
Contractor: Trine Construction Corp.
Awarded Contract Amount: $2,070,995.00
Funding Sources: Water & Sewer Fund and Capital Projects Fund

Project Information

 


This Project Includes:  5,580 linear feet of 8" watermain, valves, vaults, hydrants and other associated work.  New sidewalks and fiber lines will be installed along each roadway, and driveway aprons will be replaced as needed.  All roadways will be either be reconstructed or resurfaced.

Project Limits: Glenn Avenue, Carpenter Avenue, Shepard Avenue. 

Project Schedule:
TBD
  1. Lana Rudnik

    Contract Assistant
    Phone: 847-279-6912

Communications


Notify Me: Residents within the construction areas are encouraged to sign up for Notify Me to receive periodic updates regarding construction in their area.  Click here to sign up.

Newsletters & Notices: Periodically newsletters and notices are distributed to residents to keep them apprised of current and upcoming construction related events.

Project Updates



6.23.17
As part of the 2017 Watermain Replacement Project, the contractor will be working at the intersection of Glenn Ave and Hintz Road on June 26th and 27th.  The work will require a road closure on Glenn Avenue at the intersection of Hintz Road.  The traffic will be redirected to Chaddick Drive with local traffic only between Shepard Avenue and the road closure at Hintz Road.  Road closure and detour signs will be placed per IDOT standard.

5.30.17
New watermain on Shepard Avenue is in service and the fire hydrants are operational.  New watermain on Carpenter is installed and the pressure test is scheduled.  Work continues on Glenn Avenue.

5.30.17
Work continues on Shepard Avenue and Carpenter Avenue and Glenn Avenue.

5.11.17
Watermain construction work is scheduled to commence on May 15th on Shepard Avenue.  On Tuesday, May 16th, a second construction crew will begin work at the end of Carpenter Avenue.