2024 Lakeside Villas Street Resurfacing Program
General Information
| Tentative Start Date: | July 15,2024 |
| Tentative Completion Date: | End of August |
| Bid Opening: | May 21, 2024 |
| Project Manager: | Kevin Pelli |
| Contractor : | Chicagoland Paving Contractors., Inc. |
| Award Contract Amount : | $415,000 |
| Funding Sources : | Water Capital Improvements |
Project Information
This Project Includes: the removal and replacement of some public sidewalk squares associated with ADA compliancy, removal and replacement of some identified curbing, along with grinding and paving of the streets within the Lakeside Villas subdivision.
Project Location: Lakeside Villas
Updates:
7-15-24: Contractor began sawcutting curbs and sidewalks to be replaced.
7-19-24: Chicagoland Paving has completed the curb and public sidewalk removals at the following locations, Westwood Court, Candlewood Court, Bayside Drive and Bayside Lane. These additional locations have been barricaded and cordoned off with caution tape. Chicagoland Paving is now beginning to remove all unsuitable materials from today’s excavated locations and yesterday’s excavated locations. On Saturday, July 20th, Chicagoland Paving will be continuing with the removal of the unsuitable materials at the remaining locations that didn’t get completed today. Next week, the sewer contractor will begin all of the storm sewer adjustments and rehabilitation work.
7-24-24: Chicagoland Paving continued with the identified curb removals. To date, 75% of the identified curb on this project has been removed and 100% of the public sidewalk locations on this project have been removed. The remaining curb to be removed is located on Lakeside Circle Drive, Bayside Lane, Bayside Court, Clearwater Lane and Cedarwood Lane.
7-26-24: Emergia Construction, completed the identified storm sewer rehabilitation work within the Lakeside Villas Subdivision.
8-3.24: Carrera Concrete, has just completed pouring all of the public sidewalk squares, along with the placement of all required ADA panels at every affected corner.
8-5-24: New NPTPO signage was just posted on Lakeside Circle Drive, Bayside Lane, Bayside Court, Clearwater Lane and Cedarwood Lane. This signage will remain in place until the end of the day on Friday, August 9th, Tomorrow, starting at approximately 7:15am, Chicagoland Paving will begin the process of removing the remaining 500+ linear feet of concrete curbs on the aforementioned streets. This work will last 2 days, Tuesday and Wednesday. Carrera Concrete has confirmed that they will be removing all of the framing from last Saturday’s concrete pour, on Thursday. They will also be stoning, framing and pouring the curb that’s being removed on Tuesday and Thursday of this week. They are planning on all of the concrete associated with this project to be poured out by the end of the day on Friday. Please remember that all of the NPTPO signage will go into effect starting at 7:00am tomorrow morning. The goal is to keep these specific streets and areas where applicable, free of parked cars, so that the contractors can have access and to get the work done in a safe and timely matter.
8-8-24: Carrera Concrete, has just completed the placement of 36 cubic yards of concrete, within the remaining 500 linear feet of curb, along with the ADA compliant sidewalks and curbing on Hintz Rd at Lakeside Circle Drive. Carrera Concrete, has also completed pouring the concrete wedge, between the void in the street and the face of the new curbing. Tomorrow, Carrera Concrete, will return to Lakeside Villas to strip the existing form boards and to pick up their remaining lumber and any leftover materials.
Tomorrow, Chicagoland Paving, will return to the project to backfill with stone, all of the areas in front of the public sidewalks, the driveway apron at 663 Lakeside Circle Drive and in front of the driveways that were just poured today. The affected driveway’s that were just poured today, will not be accessible until Tuesday or Wednesday of next week when the compression strength tests come back as passed and when the concrete contractor will be removing the barricades.
All of the concrete associated with this resurfacing project has been completed. Asphalt grinding is the next step and the schedule has not been finalized to date.
8-14-24: Beginning on Monday, August 19th, Chicagoland Paving, will begin milling 1 and ¾ inches of existing asphalt on all of the streets, within the Lakeside Villas subdivision. This milling will take 3 full days to complete and we’ll be doing approximately 4 streets per day, with Lakeside Circle Drive being the biggest of them all. On August, 26th, if not sooner, Emergia Construction, will return to Lakeside Villas to reset the 21 storm / sanitary sewers throughout the subdivision. This work will take between 2 and 3 days to complete.
8-16-24: On August 19th, the asphalt milling will commence at approximately 7:00am. The schedule is to mill all of Lakeside Circle Drive first and then move to Bridgeview Court and the Clearwater streets last. With this type of milling operation, there will be times when a resident or residents will not be able to leave their driveway or return to their street for a period of time, as there will be a large milling machine and trucks that will be taking up the entire street for up to an hour or more at a time, especially when the side streets are being milled.
8-20-24: Today, Chicagoland Paving, completed grinding the following streets, Bridgeview Court, Clearwater Lane, Clearwater Court, Clearwater Drive, Cedarwood Lane and Cedarwood Court. Tomorrow, starting at 7:15am, Chicagoland will begin grinding on Ivy Court, Barberry Lane, Ash Lane, Westwood Court, Candlewood Court and lastly the Bayside streets. Whatever grinding does not get completed tomorrow, will be done on Thursday, August 22nd. No Parking / Temporary Police Order signage remains in place on Ivy, Barberry, Ash and Westwood Court. New NPTPO signage was erected on Candlewood, Bayside Drive, Bayside Court and Bayside Lane. NPTPO signage was removed late this afternoon from, Bridgeview, Clearwater lane, Court and Drive, along with the NPTPO signage on Cedarwood Lane and Cedarwood Court. Residents can return to parking on these street for the foreseeable future.
8-26-24: Emergia Construction, continued with their sewer adjustment within the Lakeside Villas subdivision. Tomorrow, Emergia, will return to complete the sewer work for this resurfacing project, Emergia has ramped all of the sewer structures that were poured late last week with temporary cold patch asphalt. The sewers that are being adjusted this week will be ramped with this same cold patch this week as well. Doing this cold patch work will allow for the structures themselves to be driven over and this practice will allow for the removal of the current flashing barricades that are currently protecting these sewer structures. Today, some flashing barricades were removed from some of the streets, while new flashers protect the sewers that were adjusted and poured with concrete today.
8-29-24: Chicagoland Paving, will begin the asphalt paving within the Lakeside Villas subdivision starting at 7:00am on Wednesday, September 4th. Chicagoland Paving, will continue with the asphalt paving on Thursday, September 5th and will conclude the asphalt paving on Friday, September 6th. On Wednesday, September 4th , Chicagoland Paving, will begin paving on Bayside Lane first and the proceed forward to Bayside Court, Bayside Drive, Candlewood Court, Westwood Court, Ivy Court, Barberry Lane and conclude Wednesday’s work on Ash Lane.
9-4-24: Chicagoland Paving has started paving as scheduled starting on Bayside Lane.
9-5-24: Today, Chicagoland Paving, completed the asphalt paving on Cedarwood Court and Lane, Clearwater Drive, Lane and Court, Bridgeview Court and the eastern side of Lakeside Circle Drive. All streets that had been paved today are reopen to all through traffic. NPTPO signage does remain in place on all of the aforementioned streets, as the village does not want any overnight street parking until tomorrow, midday, which at that time, these signs will be removed. Tomorrow's planned paving operation, will begin at 670 Lakeside Circle Drive and the contractor will begin paving both sides of Lakeside Circle Drive in unison. They will pave out one side of the street to a certain point and then fall back and pave the other side of the street to connect both sides of the street while doing so intermittently.
9-6-24:Chicagoland Paving, completed the placement of the hot mix asphalt on Lakeside Circle Drive. This now completes the asphalt paving within the Lakeside Villas Subdivision. Within the past 3 days, Chicagoland Paving, placed a total of 1,744 tons of N50 surface asphalt on all of the affected streets within the Lakeside Villas subdivision.