Bike Path Improvements

General Information

Tentative Start Date:April 28th, 2023
Tentative Completion Date:May 19th, 2023
Bid Opening:March 23rd, 2023
Project Manager:Kole Kamine
Contractor:Accu-Paving Company
Awarded Contract Amount:$79325.00
Funding Sources:Capital Outlay Funds


Project Information

 

 

This Project Includes: removal of existing asphalt bike path and replacement of Hot-Mix Asphalt pavement.

Project Limits: 
South Path:
 Geneva Drive to the park district park. 

North Path:
 Geneva Drive to the bike path cul-de-sac. 

Bike Path
Updates:

5-5-23: Accu-Paving began removal of the existing asphalt bike paths. 

5-18-23: Accu-Paving completed paving the paths.